This week contractors began setting up the enclosures for the asbestos remediation in the next phase of work. This is expected to take six weeks, then plaster repairs...[read more]
Construction crews have set up scaffolding for the last phase of work on the west side of Assumption Church. This work includes the final window next to the...[read more]
The Project Management Association of Canada (PMAC) has named the Restoration of Assumption Church and Pupatello Construction as its 2022 Canadian Project of the Year in the...[read more]
Over the last several days, contractors have been moving the scaffolding forward in the church preparing for the next phase of work. This will open up the back...[read more]
Paining has started on the west side of Assumption Church. This work is expected to last until after Labour Day,...[read more]
Plaster work on the back four bays of the west side has been complete and painting is set to begin the first week of June. ...[read more]
Bishop Fabbro has written the attached letter to Parishioners of Assumption Parish. ...[read more]
Plaster work has started on the west side of Assumption Church. Workers from Star Plastering will be repairing all of the water damaged areas to prepare...[read more]
Over the next couple of weeks, restoration work will start up again on the inside of Assumption Church. The first phase of work will be in the back three...[read more]
Restoration work will pause over the winter to allow the church to have full seating over the Christmas seasons, and resume in the Spring on the west side....[read more]