Phase One – Stablization – 2019

The first phase of work includes a new copper roof, a new hot water heating system, asbestos removal and several smaller, high-priority projects.

Five area contractors submitted bids for the work and the project was awarded to Pupatello & Sons Ltd. for $1.36 million, roughly 30% below the initial projected cost.

Work Schedule:

Work is scheduled to begin before the end of May with completion in October.

The goal of the work is to stabilize Assumption Church for a return to regular use as quickly as possible.

The scope of the work includes the following items:

  • Foundation wall repairs
  • Reinforcing roof structure
  • Replacement of deteriorated floor joists
  • Fireproofing boiler room
  • Asbestos remediation
  • Upgrade alarm and exit lighting
  • Replace domestic water supply
  • Install new hot water heating system
  • Remove redundant exterior electrical wiring
  • New long-term roof (copper shingle)