PHOTOS: Restoration Update June 29th, 2019

Please note, this post is 2636 days old.

The information listed in this post may be out of date. It has been preserved here for historical purposes.

Categories: Restoration News

Double AA roofing has removed all of the old asphalt shingle roof, and have installed new plywood and new ice and water shield.

The installation of the copper shingle roof is slated to start in early July with the roof completed by mid-July, weather permitting.

Meanwhile, under the church crews from R.C. White continue to work on asbestos removal. This is scheduled to be completed by mid-August.